Sisi inspects quartz production complex in Ain Sokhna

Thursday، 25 May 2023 - 03:19 PM

President Abdel Fattah El Sisi inspected on Thursday a quartz production complex in Ain Sokhna, in the Suez governorate.

During the inspection tour, Sisi stood on all details about the complex and the stages of production.

The complex groups four factories established on an area of about 66 feddans. 

President Sisi stood on all details about the quartz production complex and the production stages.

The complex includes a quartz primary crushing factory which was set up on an area of 12,000 square meters with a production capacity of 140,000 tons annually.

The complex includes an area for storing quartz output in addition to a factory for producing quartz panels at a production capacity of 438,000 tons annually.

About 40 percent of the complex's area is green landscape.

The president listened to Ibrahim Mahfouz, the official in charge to two coal factories in the complex, who explained the stage of the quartz production in the two factories.

During the inspection tour of Quartz production complex, Sisi listened to a detailed presentation on the production of high-quality quartz panels.

Moustafa Hassan, the one in charge of the production line, informed Sisi that 19 panels of quartz are being produced per hour.

He explained that the quartz ore is being processed in four units, the first of which is of capacity of 2,400 meters and it takes 11 minutes.

Then the quartz mixture is unloaded in another unit to crush all blocs that could block the molding process.

He added that latest-of-the-art equipment is being used in the quartz production.

At the end of the tour, the President inspected an exhibition of the Egyptian Mining Company. 